Install 1180 meters of 150mm to 200mm DI watermain, 1,200 meters of 200mm to 675mm sanitary sewer, 1280 meters of DR35 PVC storm sewer, c/w curb, sidewalk and road restoration.
Completion Date: November 2020
Start Date: May 2020
Client: City of Burnaby, Todd Bowie, RF Binnie, 778-908-6539