Date Posted : June 26, 2024


Complete Utility Contractors is currently undertaking a sewer separation project for the City of Vancouver. As a part of Hastings Sunrise Sewer Renewal - Green Rainwater Infrastructure project, we are replacing old combined sewer lines with upgraded storm and sanitary sewer pipes.


Sewer Separation in Vancouver


  • Completion Date: November 2025
  • Start Date: December 2023
  • Client: City of Vancouver

When completed, we will have dug over 3 kilometers of twin trenches and laid down over 6 kilometers pipes, including 450mm and 1050mm concrete storm and sanitary pipes.

At certain sections we are digging and excavating up to 7 meters deep. Installation of green infrastructure assets, including drywells, infiltration trenches, and bioretention bulges, will also be within the scope of the project.