Date Posted : February 13, 2025


Surrey city council awarded this $7.6 million contract to Complete Utility Contractors for the construction of roughly 2,900 metres of HDPE sanitary sewer forcemains in Bear Creek and Quibble Creek.



  • Completion Date: September 2025
  • Start Date: January 2025
  • Client: City of Surrey

Our crew is excavating and installing a 750mm and 700mm HDPE twin force main through Holland Park in Surrey to kick start our Bear Creek Force Main project. This project includes a large transition chamber and deep sewer installation.

Currently sewage from parts of the City Centre and Newton flows south, conveyed through an aging trunk sewer that was built in 1970 and it has reached its capacity.